Re: : Jurisdictions That REQUIRE Engineer's Observations
[Subject Prev][Subject Next][Thread Prev][Thread Next]- To: <seaint(--nospam--at)seaint.org>
- Subject: Re: : Jurisdictions That REQUIRE Engineer's Observations
- From: "Jim Getaz" <jgetaz(--nospam--at)shockeyprecast.com>
- Date: Thu, 30 Oct 2008 07:53:22 -0400
|
Davis, Your
“Based on all the technical information and test reports received along
with my personal site visits, it is my professional opinion...” sounds a
lot like the weasel words we use when asked for this kind of certification. As
a precast concrete subcontractor with PEs on staff but a lot of consultants
designing Design-Build projects, we sometimes have to “certify”
construction, and it is occurring with increasing frequency. We say we depend
on our PCI certified QC department’s inspections, our PCI certified
erector’s daily reports, our field coordinator’s inspection, our
field QC inspection and at least one engineer’s field observation to say
that everything is in accordance with the erection drawings and the remedial
details. The only issue is that the requirement usually wants this from the
design engineer, who often works for a consultant. Now some of our consultants
make a practice of visiting their sites during erection, but their insurance
carriers still do not like it. So we do. So far, no AHJ has rejected our
letter. I
have never been aware at the start of a project that this would be required,
but since the GC usually still has a lot of our money when the request is
received, we comply. Jim
Getaz Winchester,
Virginia |
- Prev by Subject: Re: 2007 CBC Section 1805.7.2.1
- Next by Subject: ACI 318-08 Section 14.8 Alternate Design of Slender Walls
- Previous by thread: Re: 2007 CBC Section 1805.7.2.1
- Next by thread: Elevator load factor.
- About this archive
- Messages sorted by: [Subject][Thread][Author][Date]