Re: Cranes and earthquake loads
[Subject Prev][Subject Next][Thread Prev][Thread Next]- To: seaint(--nospam--at)seaint.org
- Subject: Re: Cranes and earthquake loads
- From: "Geoffrey G. Melchor" <melbec(--nospam--at)saipan.com>
- Date: Wed, 30 Sep 1998 23:20:01 -0700
When earthquake strike while crane is working, can you stop the crane immediately? If not then there is a load from the crane and at the same time from the earthquake. Geoffrey Melchor W&K Engineers Gudrun Olafsdottir wrote: > > Here goes my first question to the list: > > I have been asked whether a crane in a steel-frame building > we have been designing needs to be designed for earthquake > loads. I can't find anything about cranes in our earthquake > code so I was wondering what is done elsewhere and also if > anyone has had any experience with this. > > Thanks in advance for any information! > > Gudrun Olafsdottir > > Hnit Consulting Engineers Ltd. > Reykjavik, Iceland >
- Prev by Subject: Re: cracks repair @ brick walls
- Next by Subject: Fwd: Dam
- Previous by thread: Long Beach Wood Fair
- About this archive
- Messages sorted by: [Subject][Thread][Author][Date]